Licensing and regulation (1667)
More...
Additional Info
-
Decision
Decision Report - granted 9 June 2022
- Type Works approval
- Holder JD Organics T/A GO Organics
- Premises name Garden Organics
- Location details Part Lot 12 on Diagram 92147, 276 Aurisch Road
- Suburb BOONANARRING WA 6503
- Local Government Gingin Shire
- Date issued 2022-06-09
- Date commenced 2022-06-09
- Date of expiry 2027-06-08
- Category 61 - Liquid waste facility, 61A - Solid waste facility, 67A - Compost manufacturing and soil blending
- Comment Works Approval granted 9 June 2022
Additional Info
-
Decision
Amendment Report - granted 5 January 2023
Amendment Report - granted 17 April 2023
- Type Works approval
- Holder Australian Nickel Investments Pty Ltd
- Premises name Cosmos Nickel Operations – Paste Plant
- Location details Goldfields Highway, Mining tenement M36/371 and part mining tenements M36/127 and M36/180 as defined by the premises map in Schedule 1
- Suburb SIR SAMUEL WA 6437
- Local Government Leonora Shire
- Date issued 2023-04-17
- Date commenced 2022-02-18
- Date of expiry 2027-02-17
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Works Approval amendment granted 17 April 2023
Additional Info
-
Decision
Decision Report - Granted 10 March 2022
Amendment Report - Granted 04 March 2025
- Type Works approval
- Holder Boab Metals Limited
- Premises name Boab Metals Limited
- Location details Part of the Mining Lease M80/286
- Suburb KUNUNURRA WA 6473
- Local Government Wyndham-East Kimberley Shire
- Date issued 2025-03-04
- Date commenced 2022-03-11
- Date of expiry 2028-03-10
- Category 12 - Screening of material
- Comment Works Approval amendment granted 04 March 2025
Additional Info
-
Decision
Decision Report - granted 10 April 2025
- Type Works approval
- Holder Bunbury Water Corporation T/A Aqwest
- Premises name Bunbury Recycled Water Treatment Plant
- Location details Part of Lot 5262 on Deposited Plan 183085, Minninup Road
- Suburb DALYELLUP WA 6230
- Local Government Bunbury City
- Date issued 2025-04-10
- Date commenced 2025-04-10
- Date of expiry 2030-04-09
- Category 54 - Sewage facility
- Comment Works Approval granted 10 April 2025
Additional Info
-
Decision
Amendment Report - granted 19 July 2023
Amendment Report - granted 24 August 2023
Amendment Report - granted 04 June 2025
Amendment Report - granted 10 November 2025
- Type Works approval
- Holder Aurenne MIT Pty Ltd
- Premises name Mt Ida Gold Project; Bottle Creek Premises
- Location details Mining tenements: M29/150, M29/151, G29/29, G29/30, L29/145, L29/154, L29/137, E29/1007, E29/1014
- Suburb MENZIES WA 6436
- Local Government Menzies Shire
- Date issued 21-06-2022
- Date commenced 21-06-2022
- Date of expiry 19-12-2026
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore, 7 - Vat or in situ leaching of metal, 64 - Class II or III putrescible landfill site
- Comment Works approval amendment granted 10 November 2025
Additional Info
-
Decision
Amendment Report - granted 30 January 2025
Amendment Report - granted 30 May 2025
- Type Works approval
- Holder Pilbara Iron Company (Services) Pty Ltd
- Premises name Paraburdoo Iron Ore Mine, Eastern Range Project and the Western Range Project
- Location details AML70/246, L47/326, AG70/4, AG70/14 and AML70/4
- Suburb ROCKLEA WA 6751
- Local Government Ashburton Shire
- Date issued 2022-08-19
- Date commenced 2022-08-19
- Date of expiry 2026-08-31
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore, 12 - Screening of material, 64 - Class II or III putrescible landfill site, 73 - Bulk storage of chemicals etc.
- Comment Licence amendment granted 30 May 2025
Additional Info
-
Decision
Decision Report - granted 24 June 2022
- Type Works approval
- Holder AWE Perth Pty Ltd
- Premises name Waitsia Gas Project Stage 2 (WGP2) Produced Water Reinjection
- Location details Part of Lot 4 on Plan 13178, Lot 3 on Plan 13178 and Lot 32 on Deposited Plan 74421, Rye Road
- Suburb MOUNT ADAMS WA 6525
- Local Government Irwin Shire
- Date issued 2022-06-24
- Date commenced 2022-06-24
- Date of expiry 2027-06-23
- Category 11 - Oil or gas production (other)
- Comment New Works Approval granted 24 June 2022
Additional Info
-
Decision
Amendment Report - granted 07 November 2023
- Type Works approval
- Holder Australian Potash Limited
- Premises name Lake Wells Potash Project
- Location details Part of M38/1275 and M38/1274
- Suburb LAVERTON WA 6440
- Local Government Laverton Shire
- Date issued 2022-07-28
- Date commenced 2022-07-28
- Date of expiry 2027-07-27
- Category 85 - Sewage facility, 89 - Putrescible landfill site
- Comment Works approval amendment granted 07 November 2023
Additional Info
- Decision
- Type Works approval
- Holder Wiluna Operations Pty Ltd
- Premises name Wiluna Mine Site
- Location details Within Mining Leases M53/32, M53/96, M53/200, M53/26, M53/40 and M53/50, As defined by the Premises Map in Schedule 1
- Suburb WILUNA WA 6646
- Local Government Wiluna Shire
- Date issued 2022-08-17
- Date commenced 2022-08-17
- Date of expiry 2027-08-17
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore, 63 - Class I inert landfill site, 64 - Class II or III putrescible landfill site
- Comment Works Approval granted 17 August 2022
Additional Info
- Decision
- Type Works approval
- Holder Paulsens East Iron Ore Pty Ltd
- Premises name PEIO Project Transshipment Facility
- Location details Warrirda Road, As defined by the coordinates in Schedule 2 as depicted in Schedule 1
- Suburb ONSLOW WA 6710
- Local Government Ashburton Shire
- Date issued 2023-01-05
- Date commenced 2023-01-05
- Date of expiry 2027-01-04
- Category 58 - Bulk material loading or unloading
- Comment Works Approval granted 5 January 2023
Additional Info
- Decision
- Type Works approval
- Holder Onslow Iron Pty Ltd
- Premises name West Pilbara Iron Ore Project
- Location details Tenement L08/68, As defined by the premises maps in Schedule 1
- Suburb CANE WA 6710
- Local Government Ashburton Shire
- Date issued 2022-10-04
- Date commenced 2022-10-04
- Date of expiry 2027-10-03
- Category 12 - Screening of material
- Comment Works Approval granted 4 October 2022
Additional Info
- Decision
- Type Works approval
- Holder Veolia Recycling and Recovery (Perth) Pty Ltd
- Premises name Veolia Recycling and Recovery (Perth) Pty Ltd
- Location details 6264 Albany Highway, Lot 2 on Plan 2767 Albany Highway
- Suburb NORTH BANNISTER WA 6390
- Local Government Boddington Shire
- Date issued 2022-08-25
- Date commenced 2022-08-25
- Date of expiry 2027-08-25
- Category 67A - Compost manufacturing and soil blending
- Comment Works Approval granted 25 August 2022
Additional Info
-
Decision
Amendment Report - granted 15 July 2025
Revised Amendment Report - granted 5 December 2025
- Type Works approval
- Holder Yuri Operations Pty Ltd
- Premises name Project Yuri
- Location details Lot 564 Village Road, Part of Lot 564 on Deposited Plan 31023 As defined by the premises map in Schedule 1
- Suburb BURRUP WA 6714
- Local Government Karratha City
- Date issued 18-08-2022
- Date commenced 19-08-2022
- Date of expiry 31-12-2026
- Category 31 - Chemical manufacturing
- Comment Revised Works Approval amendment granted 05 December 2025
Additional Info
-
Decision
Decision Report - granted 04 August 2022
Amendment Report - granted 04 June 2025
- Type Works approval
- Holder Nifty Copper Pty Ltd
- Premises name Nifty Copper Project
- Location details M271SA
- Suburb TELFAR WA 6762
- Local Government East Pilbara Shire
- Date issued 2022-08-04
- Date commenced 2022-08-05
- Date of expiry 2027-08-04
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore, 7 - Vat or in situ leaching of metal
- Comment Works Approval amendment granted 04 June 2025
Additional Info
-
Decision
Decision Report granted 7 July 2022
- Type Works approval
- Holder Newcam Minerals Pty Ltd
- Premises name Mt Gould Iron Ore Project
- Location details Mining Tenement M52/236 Landor – Meekatharra Road
- Suburb PEAK HILL WA 6642
- Local Government Meekatharra Shire
- Date issued 2022-07-07
- Date commenced 2022-07-07
- Date of expiry 2027-07-07
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Works Approval granted 7 July 2022
Additional Info
-
Decision
Amendment Report - granted 29 August 2025
- Type Works approval
- Holder Covalent Lithium Pty Ltd
- Premises name Earl Grey Lithium Project IWL/TSF
- Location details Marvel Loch-Forrestania Road (Mining tenement G77/137, M77/1066 and M77/1080 as depicted in Figure 1, Schedule 1.)
- Suburb MOUNT HOLLAND WA 6426
- Local Government Yilgarn Shire
- Date issued 2022-11-28
- Date commenced 2022-11-28
- Date of expiry 2027-11-28
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Works approval amendment granted 29 August 2025
Additional Info
- Decision
- Type Works approval
- Holder Northern Star (HBJ) Pty Ltd
- Premises name South Kalgoorlie Operations - Jubilee Gold Mine
- Location details Lot 15 on Plan 58833, Lot 50 on Plan 226299 and Lot 51 on Plan 226303, Lot 103 on Plan 40395 Lot 105 on Plan 40396, and mining tenements M26/118, M26/143, M26/204 and M15/456
- Suburb KALGOORLIE WA 6430
- Local Government Kalgoorlie-Boulder City
- Date issued 2023-05-10
- Date commenced 2023-05-10
- Date of expiry 2028-05-09
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Works Approval granted 10 May 2023
Additional Info
-
Decision
Amendment Report - granted 13 December 2022
- Type Works approval
- Holder B & J Catalano Pty Ltd
- Premises name B & J Catalano Pty Ltd
- Location details Eatha Road (Part of Lot 42 on Deposited Plan 410794 Certificate of Title Volume 2929 Folio 44 As defined by the premises maps depicted in Schedule 1.)
- Suburb CHITTERING WA 6084
- Local Government Chittering Shire
- Date issued 2022-08-16
- Date commenced 2022-08-16
- Date of expiry 2027-08-16
- Category 12 - Screening of material
- Comment Works Approval amendment granted 13 December 2022
Additional Info
- Decision
- Type Works approval
- Holder Water Corporation
- Premises name East Rockingham Water Resource Recovery Facility
- Location details Lot 501 on Deposited Plan 61891 Chesterfield Road and Pipeline Outlet Corridor located on Lot 502 Vol 2733 Folio 845 Deposited Plan 61891 Patterson Road East
- Suburb ROCKINGHAM WA 6168
- Local Government Rockingham City
- Date issued 2022-10-27
- Date commenced 2022-10-27
- Date of expiry 2027-10-26
- Category 54 - Sewage facility
- Comment Works Approval granted 27 October 2022
Additional Info
- Decision
- Type Works approval
- Holder Shire of East Pilbara
- Premises name Newman Wastewater Treatment Plant
- Location details Great Northern Highway, Lot 568 on Deposited Plan 418655
- Suburb NEWMAN WA 6753
- Local Government East Pilbara Shire
- Date issued 2024-05-09
- Date commenced 2024-05-09
- Date of expiry 2029-05-09
- Category 54 - Sewage facility
- Comment Works approval granted 09 May 2024
Additional Info
-
Decision
Amendment Report - granted 22 July 2025
- Type Works approval
- Holder Regis Resources Ltd
- Premises name Duketon Gold Project
- Location details M38/498 and M38/499 Shire of Laverton (As defined by the premises maps attached in Schedule 1)
- Suburb LAVERTON WA 6440
- Local Government Laverton Shire
- Date issued 2022-11-16
- Date commenced 2022-11-17
- Date of expiry 2027-11-16
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Works Approval amendment granted 22 July 2025
Additional Info
-
Decision
Decision Report - Granted 27 September 2022
- Type Works approval
- Holder Water Corporation
- Premises name Lloyd Street North Wastewater Pumping Station Plant
- Location details Lot 334 on Diagram 77554, and Part of Road Reserve, Lloyd Street
- Suburb MIDDLE SWAN WA 6056
- Local Government Swan City
- Date issued 2022-09-27
- Date commenced 2022-09-27
- Date of expiry 2027-09-27
- Category 85A - Sewage pumping station
- Comment Works Approval granted 27 September 2022
Additional Info
-
Decision
Amendment Report - granted 12 December 2024
- Type Works approval
- Holder LRL (AUST) Pty Ltd
- Premises name Kathleen Valley Lithium-Tantalum Project
- Location details Mining tenements M36/265, M36/459, M36/460, M36/696, G36/52, L36/255, L36/256
- Suburb LEONORA WA 6438
- Local Government Leonora Shire
- Date issued 2022-09-28
- Date commenced 2022-09-28
- Date of expiry 2027-09-27
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore, 52 - Electric power generation, 54 - Sewage facility, 89 - Putrescible landfill site
- Comment Appeal period commences 16 December 2024
Additional Info
-
Decision
Decision Report - Granted 13 September 2022
- Type Works approval
- Holder IB Operations Pty ltd
- Premises name North Star Stage 2 – Junction Camp WWTP
- Location details Great Northern Highway, Part of Miscellaneous Licence 45/625 IRON BRIDGE JUNCTION As defined by the coordinates in Schedule 1
- Suburb MARBLE BAR WA 6760
- Local Government East Pilbara Shire
- Date issued 2022-09-09
- Date commenced 2022-09-12
- Date of expiry 2027-09-12
- Category 54 - Sewage facility
- Comment New Works Approval granted 13 September 2022
Additional Info
-
Decision
Amendment Report - granted 18 July 2024
- Type Works approval
- Holder Kalgoorlie Consolidated Gold Mines Pty Ltd
- Premises name Fimiston Processing Plant
- Location details Tenements M26/383, M26/294, M26/359, M26/86, M26/46, L26/216, L26/217, G26/159
- Suburb KALGOORLIE WA 6430
- Local Government Kalgoorlie-Boulder City
- Date issued 2022-10-12
- Date commenced 2022-10-12
- Date of expiry 2029-10-11
- Category 5 - Processing or beneficiation of metallic or non‑metallic ore
- Comment Appeal period commences 22 July 2024